Reply To: Plant Hours for Strip Footings

Home Forums 9. Material Conversions Plant Hours for Strip Footings Reply To: Plant Hours for Strip Footings

#40080
John Brock
Keymaster

Hi Terry- Sorry I missed this post.

I would use Profile Builder to model the footings OR Takeoff_Length to accumulate lengths if mass modeled footings. In Estimator, Layers Tab, I would use attribute of Meters for either the PB Layer or the Takeoff_Length Layer. Multiplier should be “/15” and unit of Hrs. and either round up or not. Does this help?